Cancellation and Postponement of Major Projects under Saudi Law: Between Risk Management and the Protection of Contractual Rights
General
How Saudi law treats cancelling and postponing major projects: termination vs suspension, Civil Transactions Law, procurement rules, FIDIC and risk tools.
Summary: This article examines the cancellation and postponement of major projects under Saudi law. It distinguishes between termination and suspension, sets out the relevant provisions of the Civil Transactions Law, the Government Tenders and Procurement Law and FIDIC contracts, and highlights the main risks, the most common mistakes, and the tools available to protect both contractor and owner.
Many construction dispute files begin with a single sentence: “The project has stopped, and we don’t know exactly what our rights are.” The problem is rarely the stoppage itself; it usually lies in a contract that never anticipated it, or one that addressed it in general terms that offer little help when they are needed. The problem is magnified in major projects, where contracts run for years and involve dozens of contractors, suppliers and financiers. Here we explain the difference between cancelling and postponing major projects, where the risks are concentrated, and what contractors and owners can do to protect their positions in major projects before a dispute arises.
Cancelling Major Projects Is Not Postponing Them
When a contract is cancelled, the parties’ future obligations come to an end and all that remains is to settle the work already performed. Postponement, by contrast, is a temporary suspension: the contract remains in force even though work on site has stopped. Confusing the two is costly, because in major projects the applicable clause determines the notice deadlines, extensions of time, the calculation of compensation, and the fate of bank guarantees.
The Legal Framework for Cancelling and Postponing Major Projects
In major projects, the first point of reference is the contract. Where the contract is silent, the Civil Transactions Law, issued by Royal Decree No. (M/191) dated 29/11/1444 AH, applies(1). This Law contains no general provision on suspension, so claims for time and cost rest on good faith and on the rules governing breach and compensation. Termination of a construction (muqawala) contract, however, has its own grounds under Articles 475–478. These include an unforeseen excuse, in which case the party seeking termination compensates the other party, and the contractor’s inability to complete the work for a reason beyond its control, in which case it is entitled to the value of the work performed and its expenses to the extent the owner has benefited from them(2).
In a lump-sum construction contract, Article 471 allows the court to restore the contractual balance where it has been disrupted by general exceptional circumstances(2), while Article 97 allows renegotiation and the reduction of an onerous obligation to a reasonable level, and the parties may not agree otherwise(1). These provisions carry particular weight in major projects, which are priced years before execution.
In government major projects, the Government Tenders and Procurement Law, issued by Royal Decree No. (M/128) dated 13/11/1440 AH, also applies(3). Under this Law, the contractor’s time is extended if the government entity suspends all or part of the work for a reason not attributable to the contractor, or if the annual budget allocations are insufficient to complete the work on time, and in such cases the contractor is exempt from delay penalties (Article 74). Variation orders are limited to an increase of no more than 10% of the contract value or a reduction of no more than 20% (Article 69), so the entity cannot reduce the scope of major projects without limit, and omitted work generally may not be transferred to another contractor without an express provision(2). The General Panel of the Supreme Court (Decision No. 45/M, dated 8/5/1442 AH) has also ruled that penalty clauses are not to be applied where the pandemic caused the delay, and that the project is not to be withdrawn from the contractor on that ground(4).
FIDIC Contracts in Major Projects
FIDIC contracts, the most widely used form in major projects, distinguish between suspension of work on the Engineer’s instruction and termination of the contract. If a suspension exceeds 84 days, the contractor may request permission to proceed; if permission is not given within 28 days, the contractor may treat the suspended part as an omission, or terminate the contract if the suspension affects the whole of the works. FIDIC also allows the owner (the Employer) to terminate for convenience, but not in order to execute the works itself or to have them executed by another contractor(5).
Why Do Disputes Multiply in Major Projects During Rescheduling?
Because the decision rarely has a single cause: it may be a funding crisis, a change in the owner’s priorities, or a regulatory development. Where there is no clear wording, each party interprets the general terms in its own favour, and disputes begin over the equipment on site, subcontractors’ obligations, and compensation. The risks in major projects are concentrated in three areas: the absence of a mechanism to value the work completed at the moment of stoppage, the absence of a time limit on suspension before it becomes a de facto termination, and weak documentation at that moment.
Protection Tools in Major Project Contracts
The contractor needs the right to give immediate notice when a suspension order is issued, to claim an extension of time and its actual costs, and to suspend work if its payments are delayed. The owner needs a time limit on suspension before the contractor becomes entitled to terminate, and needs compensation to be tied to a neutral technical report. These tools must be written into major project contracts before signing; once a dispute arises, each party negotiates from a weaker position.
Where the cause of the stoppage lies beyond the control of both parties, such as a natural disaster or an emergency government decision, the force majeure clause governs. If performance becomes impossible for a reason beyond the obligor’s control, the obligation is extinguished and the contract is automatically rescinded (Article 110), although the parties may agree that the obligor bears that risk (Article 174)(1). That is why, in major projects, this clause deserves detailed drafting rather than borrowed boilerplate.
Recurring Mistakes in Major Projects
The most common mistake is relying on oral notice alone, which later makes it difficult to prove when the stoppage became known. Some contractors, keen to preserve the relationship, take on additional obligations without a written reservation, and this is later construed as an implied waiver. Some owners treat postponement as an internal decision that requires no notice, only to face broader claims than they expected. The remedy in major projects is simple: written notice through the channels specified in the contract, an express reservation of rights when continuing under protest, and specialist review before any notice is sent.
Two Hypothetical Examples from Major Projects
Suppose a contractor on one of the major infrastructure projects receives a postponement order because funding has been delayed, and keeps its equipment and workforce on site without giving formal notice. If the stoppage becomes prolonged, a documented notice recording its date and the cost of keeping the equipment on site, together with an express reservation of its right to compensation, gives the contractor a reasonable chance of recovering a large part of those costs; costs incurred before the notice, however, are harder to prove.
Now suppose the owner of a real estate development among the major projects cancels part of the works without updating the bill of quantities or settling outstanding payment applications, and the parties then disagree on the percentage of completion. Here, appointing a neutral engineering firm to record the percentage in a joint report may be the shortest route to settlement, without lengthy arbitration.
Cancellation vs Postponement in Major Projects: A Quick Comparison
| Criterion | Full Cancellation | Temporary Postponement |
|---|---|---|
| Fate of the contract | Ends permanently | Remains in force |
| Basis | Termination clause or material breach | Suspension clause |
| Compensation | Comprehensive final settlement | Costs of the stoppage period |
| Bank guarantees | Settled according to the termination terms | Usually remain in force |
| Likelihood of dispute | High if the reasons are not documented | Moderate if a time limit is set |
Conclusion
In our view, the next phase of major projects in the Kingdom will be less about widespread cancellation than about rescheduling and phased delivery, which makes the suspension and scope-variation clauses more important in practice than the termination clause. The right time to review major project contracts is before a stop order is issued, not after.
Frequently Asked Questions about Major Projects
What is the essential difference between cancelling and postponing major projects?
Cancellation ends the contract and the parties’ rights are settled in one go, whereas postponement suspends performance while the contract remains in force until the cause of the stoppage is removed.
Is the contractor entitled to compensation for postponement?
Yes, if the contract so provides or the cause is attributable to the owner. Compensation usually covers the cost of keeping equipment and labour on site and documented direct losses. In government major projects, the contractor is also granted an extension of time if the entity suspends the work for a reason not attributable to the contractor.
Can the owner in major projects terminate the contract without cause?
That depends on the contract: Saudi courts generally give effect to a termination-for-convenience clause where it is expressly provided for, unless it is exercised in bad faith(6). Compensation is governed by the parties’ agreement; where the contract is silent, the court assesses it according to the extent of the harm.
Sources
- Civil Transactions Law, issued by Royal Decree No. (M/191) dated 29/11/1444 AH.
- Pinsent Masons, Out-Law analysis of termination, suspension and scope reduction in Saudi projects.
- Government Tenders and Procurement Law, issued by Royal Decree No. (M/128) dated 13/11/1440 AH.
- General Panel of the Supreme Court, Decision No. (45/M) dated 8/5/1442 AH.
- FIDIC, Conditions of Contract for Construction (Red Book), 1999 and 2017 editions.
- Freshfields, blog post on the termination of construction contracts under Saudi law, 24 May 2022.