Construction Contracts
General
Picture a contractor who promised a residential building in 12 months and delivered it in 18. The employer wants the full delay penalty; the contractor blames late payments and the employer's changes. Settling it depends on the contract, the governing law and what each side put in writing.
Construction Contracts in Saudi Arabia: The Roots of Disputes
Picture a contractor who promised a residential building in 12 months and delivered it in 18. The employer wants the full delay penalty; the contractor blames late payments and the employer's changes. Settling it depends on the contract, the governing law and what each side put in writing.
Two Legal Regimes, Not One
Private construction contracts fall under the Civil Transactions Law (Royal Decree No. M/191), in force since 16 December 2023. Its Articles 475 to 478 govern how a muqawala (works) contract ends.
Government construction contracts follow the Government Tenders and Procurement Law (Royal Decree No. M/128 of 1440H), its Implementing Regulations and the Ministry of Finance's standard forms. A new law (Royal Decree No. M/76 dated 27/2/1448H), published in the Official Gazette (Umm al-Qura) on 4 September 2026, takes effect on 2 January 2027; until then, the current law applies.
Upcoming Changes for Government Construction Contracts
Article 70 of the new law cuts the delay penalty cap for non-supply contracts from 20% to 15% of contract value, while supply contracts stay at 6%. A higher cap needs the Minister's prior approval, disclosed to bidders before bidding. Article 71 sets a 15% cap for deficient performance in continuous service contracts, and Article 67 allows new items up to 10% of contract value, with the contractor's consent, and changes to existing items up to 20%.
Article 91 bars an entity that is behind on contractor payments, and has not acted after notice from the Ministry of Finance, from issuing new awards. In my view, this may matter more than any penalty cap, since late payment often stalls projects.
Delay, Penalties and Termination of Construction Contracts
Contractor Liability for Delay
A missed deadline alone is not enough. Under the Civil Transactions Law, compensation is due only if the delay is attributable to the contractor and causes actual loss. Force majeure, and delay caused by the employer's variations or late payments, do not count against the contractor. Where both sides contributed, a court may apportion responsibility or reject the penalty altogether.
Disputes are therefore won on paper: send written notice of every delaying event promptly, as some contracts bar late extension claims.
Liquidated Damages in Private Construction Contracts
Article 178 of the Civil Transactions Law allows the parties to agree in advance on compensation for delay or non-performance. Courts can still adjust it under Articles 178 and 179 (see the first question below). Article 173 allows liability to be limited, except for fraud or gross error.
Delay Penalties in Government Construction Contracts
Under the current law, the 20% cap is in Article 72. Both procurement laws allow extensions and penalty waivers in government construction contracts in set cases (Article 74 now, Article 72 under the new law), such as suspension for reasons not attributable to the contractor, or insufficient annual appropriations. The Ministry of Finance applied this to COVID-19 delays in 2020.
Termination and Withdrawal of Work
For private construction contracts, the Civil Transactions Law allows termination by agreement (Article 105), under a contractual right (Article 106), for breach (Article 107) or for impossibility (Article 110). A contractor that cannot finish for reasons beyond its control is paid for completed work and expenses, up to the benefit the employer gained. A party that ends the contract for an emergency excuse must compensate the other.
Where general, unforeseen circumstances make performance excessively onerous, Article 97 allows renegotiation and lets a court reduce the obligation to a reasonable level, but not unilateral suspension of work.
In government construction contracts, Article 76 of the current law requires termination for bribery, bankruptcy or assignment without written approval, and permits it where the contractor fails to remedy a delay or breach within 15 days of written notice, or subcontracts without approval. Under the new law, Article 74 leaves the cure period to the Implementing Regulations, and Article 75 adds termination in the public interest, with Ministry of Finance approval and the contractor's right to compensation preserved.
One obligation outlives handover: under the Implementing Regulations of the Saudi Building Code Application Law, the supervising designer and contractor are jointly liable for ten years from the occupancy certificate for total or partial collapse and hidden defects threatening safety.
Construction Contracts at a Glance: Private vs. Government
| Issue | Private construction contracts | Government construction contracts |
|---|---|---|
| Governing law | Civil Transactions Law (M/191) | Procurement Law (M/128); new law from 2 January 2027 |
| Delay penalty cap | As agreed by the parties | 20% now, 15% under the new law, 6% for supply |
| Adjusting the penalty | Court may reduce it to actual loss (Arts. 178 and 179) | Extension and waiver in set cases |
| Termination | Agreement, breach or impossibility (Arts. 105 to 110 and 475 to 478) | Article 76 now; Article 74 under the new law |
| Late employer payment | Favours the contractor on delay | No right to suspend work |
| Decennial liability | Ten years from the occupancy certificate | Ten years from the occupancy certificate |
Construction Contracts: Common Questions
Can a court reduce the delay penalty in private construction contracts?
Yes. Liquidated damages are a pre-estimate of loss, not a punishment. If the contractor proves a smaller actual loss, the court can reduce them, or drop them if there was no loss; they can be increased only for fraud or gross error.
In government construction contracts, can the contractor stop work if payments are late?
No. The current Implementing Regulations do not allow it; the route is a formal claim for the amounts owed, while the new law bars late-paying entities from new awards.
When can the employer terminate construction contracts?
In private construction contracts, for a material breach, preferably after a written warning. In government construction contracts, in the Article 76 cases, such as failure to remedy a delay within 15 days of notice. Do not wait too long: under Article 295 of the Civil Transactions Law, a claim cannot be heard after ten years unless the law provides otherwise.
A Final Word on Construction Contracts
Most disputes over construction contracts could be avoided, in my view, with a clear extension clause, timely notices and a programme that is genuinely kept up to date. With the new law starting on 2 January 2027, contractors should check which law governs each government contract they hold.
References
This article is for general awareness, not legal advice.
Official texts
1. Umm Al-Qura. Government Tenders and Procurement Law, published 22/3/1448H (4 September 2026), Articles 67, 70 to 75, 91, 100 and 101 (in Arabic). Link
2. Umm Al-Qura. Royal Decree No. M/76 dated 27/2/1448H (in Arabic). Link
3. Umm Al-Qura. Council of Ministers Resolution No. 199 dated 21/2/1448H (in Arabic). Link
4. Government Tenders and Procurement Law, Royal Decree No. M/128 dated 13/11/1440H, Articles 72, 74 and 76. Copy published on the Qadha website (in Arabic). Link
5. Ministry of Finance. Minister of Finance thanks the leadership on the approval of the new Government Tenders and Procurement Law, 5 August 2026. Link
Legal analysis
6. Baker McKenzie. Saudi Arabia: Key changes under new Government Procurement Law, 21 October 2026. Link
7. Noqta. Saudi Arabia's New Procurement Law: What Changed and When, 6 September 2026. Link
8. Pinsent Masons. Saudi Arabia's Civil Code: need to know for construction projects, 12 January 2024. Link
9. Pinsent Masons. Major project adjustments in Saudi Arabia: termination, suspension and descoping. Link
10. DWF. Construction Insights July 2025: liquidated damages and delay under the KSA Civil Transactions Law, 9 July 2025. Link
11. Construction Management. Saudi legal sands shift, 5 June 2024. Link
12. MEED. Saudi Arabia to extend contracts amid Covid-19, 23 April 2020. Link
13. Shwra. Everything about penalty clauses in contracts under the Saudi Civil Transactions Law, updated 29 September 2025 (in Arabic). Link